Back to archive
Engineering, Procurement, and Construction (EPC)
Cathodic protection of jetties 14 and 15 and breakwater structures
Design, procurement, installation and commissioning of a cathodic protection system for 276 jetty piles with diameters ranging from 42 to 85 inches.
- Client Pars National Petrochemical Company
- Location Bushehr — Asaluyeh
- Year 2004–2005
- Scopes Cathodic Protection
Field gallery
Nearby files
Keep exploring
-
2015
Sealing Around Storage Tanks and Cathodic Protection of the Export Jetty, Gas Transmission Pipeline and Kaveh Methanol Plant
Kaveh Methanol Company
-
2015–2019
Repair and Operation of the Cathodic Protection System for Tank, Drum and Underground Pipeline Units at the Phase 13 Refinery
Techno Energy Sepehr Kish Company (Tesco)
-
2008–2009
Installation of a Densitometer and Monitoring System on the Headers of T and Azarpad Jetties
Petroleum Export Terminals Company
-
2007–2010
Conversion of the Cathodic Protection System at Azarpad Jetty from Temporary to Permanent and Implementation of a Remote Monitoring System
Petroleum Export Terminals Company
-
2023
Temporary and permanent cathodic protection inside and outside crude oil storage tanks
Makran Petrorefining Company
-
2024–
Temporary and permanent cathodic protection of pipelines and tanks of utility and offsite units of Kimia Sanat Mabna Company
Kimia Sanat Mabna Company